Project Description
The construction period of the project is 50 days. The 1st underground floor adopts reinforced concrete structure, the 1st floor above ground and the 2nd floor adopts steel structure modular building. The building is 3.6 meters high, with a total height of 12 meters. This project is a fever clinic, which needs to meet the relevant specifications of infectious disease hospitals. All rooms meet the requirements of positive and negative pressure. There is an excessive buffer between the clean area and the polluted area to protect the safety of medical staff.
Construction Time | 202008 | Project Location | Lianyungang, China |
Number of Modules | 70 | Area of Structurea | 2120㎡ |